LOCKS TO CLOSE FOR LATEST MAJOR WORKS


The Environment Agency has released details of the locks to be closed during the winter and spring for work being undertaken in its waterway investment programme.

The list, which is subject to change, includes a major closure at Whitchurch where the road bridge linking the village to Pangbourne is being rebuilt.

In all 14 locks along the non-tidal river are affected.

The details:

Grafton Lock 4 November 2013 to 28 February 2014
Replacement of the lock gates

Rushey Lock 4 November 2013 to 20 December 2013
Re-timbering of lock chamber and tail lock cut bank protection

Shifford Lock Winter 2013/14
Bank protection work to the tail lock cut

Osney Lock 4 November 2013 to 20 December 2013
Refurbishment of weir A

Iffley Lock Winter 2013/14
New support piles for tail layby

Sandford Lock Winter 2013/14
Refurbishment of the lock chamber

Abingdon Lock 6 January 2014 to 14 March 2014
Inspection and re-sheeting of the lock gates

Culham Lock 4 November 2013 to 31 January 2014
Refurbishment and inspection of the lock gates

Whitchurch Lock Winter 2013/14
Closure of the road bridge downstream of the lock for re-build

Blakes Lock 4 November 2013 to 31 January 2014
Re-sheeting and inspection of the lock gates

Shepperton Lock Winter 2013/14
Refurbishment of the lock chamber

Sunbury New Lock Late summer / early autumn
Refurbishment of the lock chamber

Teddington Skiff Lock Late spring / early summer Refurbishment of the lock gates

Teddington Barge Lock Late summer / early autumn Refurbishment of the lock walls and timbers